

Tube Lines has announced practical completion of the upgrade of a further
five stations ahead of schedule, taking the total completed to 52. Tube
Lines is now over half way through its £500 million station upgrade programme
which will see 97 out of the 100 stations across the Jubilee, Northern and
Piccadilly lines upgraded by 2010. The latest stations to
receive an overhaul are Brent Cross, Holloway Road, Old Street, Willesden Green
and Woodside Park. Dedicated engineers carried out the bulk of the station upgrades in the few
hours between midnight and the first Tube train in the morning. Working
overnight on the Tube always puts pressure on how much work can be achieved in
any one shift with time taken up at the beginning to move the equipment into
the station, and set up safely and quickly. More time is then taken a few hours
later to clean the site and exit before the first train carrying passengers to
work comes into service. The use of a small number of weekend closures enabled the teams at each
station to speed up the engineering work to complete the works ahead of the
planned completion date. The weekend closures allow the equivalent of up to ten
normal engineering shifts to be carried out in one weekend. This reduced the
disruption to local residents during the night. Tube Lines’ work is bringing many benefits to passengers. Each station now
boasts a new public address system along with improved customer information
systems. The refurbishment of the stations and platforms included structural
repairs and the re-decoration and re-tiling of walls and floors to improve the
look and feel of the stations. With an emphasis on security, there are now more
CCTV cameras and help points inside the stations. There has been a big change in the way Tube Lines carries out station
upgrades. Through better man-management, improved logistics and by bringing key
outsourced construction work in-house Tube Lines has been able to cut the cost
of a station upgrade by as much as 40% and reduce the time it takes to overhaul
a station. Tooraj Shadnia, Tube Lines’ Senior Project Manger for the station upgrade
programme said:
“These five stations were all more than 85 years old and clearly in need
of work to improve the travelling experience for the millions of passengers
using the stations each day. Not only are they brighter and cleaner but
passenger information and security systems are now up to 21st
Century standards. Getting the stations finished earlier than scheduled is a
bonus and was achieved through very careful planning by the teams who then
working tirelessly to those plans.”
52 stations have now been upgraded, with a further six due to be completed
in May this year and upgrade works due to start on another nine stations
throughout 2008.
ENDS
For further information, please contact:
Notes to Editors
Practical completion means all substantial works have been finished although
some outstanding works, such as snags, may still need resolution. These must be
completed within a 16-week contractual period.
Press office, Tube Lines: 020 7088 4848 / 07843 551 589
If you would prefer not to receive future news from Tube Lines, please send
an email to sarah.baranowski@tubelines.com
with the subject heading “Unsubscribe”.